Phoenix Data Center Construction
Customer: Compass Data Centers
Service: Project Buffering, Heavy Lifting & Rigging, Transportation, Storage
Industry: Data Center
Components: 29 Units
- Power Centers: 59,000 lbs. (5 units)
- Generator Belly Tanks: 37,095 lbs. (5 units)
- Generator Enclosures: 64,000 lbs. (5 units)
- Transformers: 15,000 lbs. (5 units)
- Cooling Towers: 27,000 lbs. (9 units)
EQUIPMENT
SCOPE OF WORK
CUSTOMER CHALLENGE
The customer was attempting to complete phase 1 of a new data center build on a tight construction schedule, which was constantly changing. To complete the first phase, 29 outdoor units needed to be transported across the country from multiple OEMs to site, without delays, and set in place. These delivery schedules were unpredictable and would ultimately lead to significant onsite delays, should equipment delivery be delayed. These 29 units are critical to the construction schedule and ultimately dictate the project completion date.
OUR SOLUTION
ProLift took ownership of all 29 units the moment they left the OEM floor. We scheduled pick ups from the OEM, transported the units across country to a secure storage location close to the project location. This allowed for any delays to only impact the storage time rather than time onsite. We then could loadout, perform last mile delivery, offload, and set each unit right when the project schedule called for it. This eliminated all delays related to transportation and equipment delivery and allowed for the project to be completed as planned.
ABOUT
ProLift Rigging is a solution based, full-service rigging and transport organization. With our rigging capabilities and industry experts, we serve a wide variety of industries across the country. We specialize in machinery moving, industrial maintenance, transportation, storage, and much more. We partner with our customers to ensure their success through our proactive, proficient, and professional approach.