Motor Removal and Installation
Motor Removal and Installation
September 2017
Location: Belews Creek, NC
Service: Rigging, Industrial Maintenance, Machinery Moving & Setting
Industry: Power Plant
Component: 3 Motors weighing 52,000 lbs. each
EQUIPMENT
65-ton Trilifter
SCOPE OF WORK
- Remove 3 motors and place on truck
- Unload motors upon return
- Install new motors
CUSTOMER CHALLENGE
Remove and replace 3 motors weighing 52,000 lbs. each. The motors are located in a very tight location and the job required experienced and certified riggers and operators to complete the task.
OUR SOLUTION
We used our 65-ton trilifters to remove and replace all 3 motors. Our team is full of experienced and certified riggers and operators, so meeting this challenge was no problem for us.
ABOUT
ProLift Rigging is a solution based, full-service rigging and transport organization. With our rigging capabilities and industry experts, we serve a wide variety of industries across the country. We specialize in machinery moving, industrial maintenance, transportation, storage, and much more. We partner with our customers to ensure their success through our proactive, proficient, and professional approach.