Altavista Power Station Fly Ash

Date

June 2017

Location

Altavista, VA

Industry

Manufacturing

IMG 0312

Equipment

175-Ton Crane, 135-Ton Crane, 100-Ton Crane, 8-Ton Carry Deck Crane

Scope of Work

  • Crane and lifting services including engineered lift and rigging plans
  • Demo of structures, equipment and piping
  • Steel erection
  • Demo modification to existing bag house hoppers
  • Structural steel erection of silo structure
  • Installation of all associated equipment, motors, pumps, conveyors, ect.
  • Installation/ welding of all piping – air and process


IMG 0312 Cone IMG 0314 IMG 0977 IMG 0982 IMG 1188 IMG 1235 IMG 1984

Customer Challenge

This was the third plant to have Fly Ash modifications completed. The first two were self-performed by the general contractor and neither were profitable. Both had long shutdowns and required about 16,000 man hours to complete.

Our Solution

We completed this job quicker and more efficiently than before. We had major completion of the project 2 weeks early with 50% less labor than the first two plants. There was a 25-day shutdown and this project was profitable. We stored all new equipment at our yard and established “just in time” deliveries to site which relieved site congestion and multiple handling. We removed all demolished structures and equipment from site in the largest possible pieces to our yard which also relieved site congestion. This was all completed without an incident.

What they're saying

We found your team of craftsmen to be extremely professional, safety conscious, highly skilled, easy to get along with, dedicated to doing the job right the first time, very efficient in their work, and extremely hard working.

Lead Project Manager

Prolift Rigging streamline proactive proficient